SURFACE PREPARATION
- The surface of application shall be free solid, clean, free of dust and level.
- The surface shall always be free of materials such as form oil, paint, dust etc., and shall be fully cured.
- Parts on the surface (iron, wood, etc.) shall be removed and these hole shall be filled with appropriate Entegre Repair Mortars.
- You may advance to application after dampening the surface.
PREPARATION of the MORTAR
- A proper amount of fluid component shall be put inside the mixing vessel (10 kg of fluid/25 kg of powder).
- Whole bag is poured to the vessel, and stirred with hand mixer until the lumps are removed.
- After resting for 5 minutes, the mortar shall be stirred again.
- ENTEGRE CHAMFERING TAPE shall be applied to the connection points of the application surfaces using EPODOL?.
- If you do not prefer chamfering tapes, bring the connection points to an oval form and reinforce them with nets.
- Fluid mortar shall be applied with a brush or a roll.
- Second coat shall be perpendicular to the first coat and shall be applied at least for 6 hours later.
- Wait 3 days for application of final coat (ceramic, screed and cement-based plaster), and take care to prevent mechanical damage to the insulation material during coating.
- If the application area is a water tank, wait at least 28 days for the curing of the product.
CONSUMPTION
1.5-2.0 kg/per m2 for single coat
(Under proper surface and ambient conditions.
It may differ as per surface specifications and application conditions.)